- Next Question:
- You're managing an industrial design project. Your project is currently in the I...
- Posted by:
- Muhammad Farooq
- 15-August-2018
A. It formally assigns the project managerB. Includes a high level milestone scheduleC. It is always created by the project managerD. It contains external constraints and assumptions
Question added by Muhammad Farooq , QA-QC MANAGER, AL Bawani contracting co.
Date Posted: 2018/08/08
Upvote (0)Views (24)Followers (2) Answers (2)Report Question
Write an Answer
Register nowor log in to answer.
- 2 Answers
by Jomar Depone , Admin Technical Executive , HTC Technical and Cleaning Services
Project Charter is not necessarily be done by the Project Manager but it identifies the level of authority of the Project Manager.
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Answer: CExplanation: The Project Charter is often created without the project manager's involvement. Sometimes it is handed to the Project Manager by the sponsor or high level manager.
Write Your Answer
More Questions Like This
Top Answer:D. Project communication channelsSee More
What is the main difference between the project charter and the preliminary scope statement?
Top Answer:A-Project Charter is the most initial phaze of project and stackholders involved in it. When say yes and... See More
Top Answer:Appreciation for the invitation. My answer is Option D.See More
Top Answer:Answer: CExplanation: The project sponsor is the person (or people) that pays for the project. Sometimes ... See More
Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.